Weekly Construction Update: October 28, 2019

October 28, 2019

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on first and fourth floors. Continued wiring transformers in electrical rooms.  Continued working on underground site electrical.  Installed light poles. Continued installing plumbing overhead on fourth floor.  Continued installing plumbing fixtures throughout building.  Continued installation of […]

Read more

Weekly Construction Update: October 21, 2019

October 21, 2019

WORK PERFORMED THIS WEEK: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on the first and fourth floors.  Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing overhead plumbing on the fourth floor. Continued installing plumbing fixtures throughout building.  Continued installation of med-gas […]

Read more

Weekly Construction Update: October 14, 2019

October 14, 2019

Work Performed This Week: Continued electrical rough-in on the first and fourth floors.  Continued installing overhead lights and trim-out on first and fourth floors. Continued wiring transformers in electrical rooms.  Continued working on underground site electrical. Continued installing plumbing overhead on fourth floor.  Continued installing plumbing fixtures throughout building.  Continued installation of med-gas booms in […]

Read more