Category: construction update

Construction Update: December 28, 2018

https://www.campbellclinic.com/construction-update-december-28-2018/

WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placing underslab aggregate on east side. STATISTICS: The crane that will be used to hang all the structural steel arrived on site this week. It arrived […]