Category: Expansion

Construction Update: August 19, 2019

August 19, 2019

WORK PERFORMED THIS WEEK Installed electrical overhead and in-wall rough-in on the first and fourth floors. Installed overhead lights on first floor.  Installed conduit for pool. Installed third floor lights and tied them off.   Wired VAV Boxes. Placed permanent power.  Mounted transformers in electrical rooms. Continued installing overhead and in-wall on first, third and fourth […]

Read more

Construction Update: August 12, 2019

August 12, 2019

WORK PERFORMED THIS WEEK Installed electrical overhead and in-wall rough-in on the first and fourth floors. Ran conduit for fourth floor O.R. rooms.  Pulled wire for lights on the third floor.  Pulled wire on first floor in café homeruns.  Wired VAV Boxes. Permanent power is in place.  Ran wire for lights in canopy.  Continued rough-in […]

Read more

Construction Update: August 5, 2019

August 5, 2019

WORK PERFORMED THIS WEEK Continued electrical overhead and in-wall rough-in on the first and fourth floors. Installed lights on the third floor. Inspected in-wall on the fourth floor. Continued working on the installation of permanent power. Wired VAV Boxes. Installed overhead and in-wall rough-in on the fourth floor. Continued insulating and fire caulking pipes. Continued […]

Read more

Construction Update: July 29, 2019

July 29, 2019

WORK PERFORMED THIS WEEK Continued installation of overhead and in-wall rough-ins on the first to the fourth floors. Pulled and tied in wires in radiation rooms. Installed lights on the third floor. Continued working on the installation of permanent power and wiring VAV Boxes. Installed plumbing in-wall and overhead rough-in on the fourth floor. Finished […]

Read more

Construction Update: July 23, 2019

July 22, 2019

WORK PERFORMED THIS WEEK: Continued installation of overhead and in-wall rough-ins on the first to the fourth floors. Pulled and tied in wires in radiation rooms. Installed lights on the third floor. Continued working on the installation of permanent power and wiring VAV Boxes. Insulated and fire caulked pipes. Installed Med Gas and third and […]

Read more

Construction Update: July 15, 2019

July 15, 2019

WORK PERFORMED THIS WEEK: Continued installation of overhead and in-wall rough-ins on the first to the fourth floors. Installed electrical feeders from the first to the fourth floors. Continued working on the installation of permanent power and wiring VAV Boxes. Insulated and fire caulked pipes. Installed Med Gas and third and fourth floors. Installed plumbing […]

Read more

Construction Update: July 1, 2019

July 1, 2019

WORK PERFORMED THIS WEEK: Continued installation of overhead and in-wall rough-ins on the first to the fourth floors. Installed electrical feeders from the first to the fourth floors. Continued working on the installation of permanent power and wiring VAV Boxes. Insulated and fire caulked pipes. Installed Med Gas and third and fourth floors. Installed plumbing […]

Read more

Construction Update: June 24, 2019

June 24, 2019

WORK PERFORMED THIS WEEK: Continued installation of overhead and in-wall rough-ins on the first to the fourth floors. Installed electrical feeders from the first to the fourth floors. Continued installation of permanent power. Wired and installed VAV boxes. Insulated and fire caulked pipes. Installed plumbing in-wall & overhead rough-in on the first through fourth floors. […]

Read more

Construction Update: June 17, 2019

June 17, 2019

WORK PERFORMED THIS WEEK: Continued installation of overhead and in-wall rough-ins on the first through fourth floors. Installed electrical feeders from the first to the fourth floors. Continued installation of permanent power. Wired VAV boxes. Tied in roof drains, insulated and fire caulked pipes. Installed med gas piping on the third floor. Installed ducts on […]

Read more

Construction Update: June 3, 2019

June 3, 2019

WORK PERFORMED THIS WEEK: Installed elevator shaft steel. Continued electrical overhead and in-wall rough-in on the first through fourth floors. Continued underground feed for the generator power. Installed plumbing in wall and overhead rough-in on the first through fourth floors. Tied in roof drains. Installed mechanical drops in the fourth-floor operating rooms. Prepped for the […]

Read more