Prepped east half of the building pad for slab pour.
Placing underslab aggregate on east side.
STATISTICS:
The crane that will be used to hang all the structural steel arrived on site this week. It arrived in several pieces and was assembled on site over two days.
After being assembled the crane was then moved into position on the southwest side of the building pad where the erection process will begin.