Category: Germantown facility

Construction Update: January 18, 2019

https://www.campbellclinic.com/construction-update-january-18-2019/

WORK PERFORMED THIS WEEK: Continued underground electrical. Continued shipping and staging steel. Continued west half steel erection. Set west half stairs. Began installing the deck on floors two and three of the west half steel. Began excavation and installation of canopy foundations. Poured canopy foundations. Continued work on west side private drive entrance. Continued underground […]


Construction Update: January 10, 2019

https://www.campbellclinic.com/construction-update-january-10-2019/

WORK PERFORMED THIS WEEK: Continued underground electrical & plumbing. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Poured the east half slab. Continued work on west side private drive entrance. Continued underground storm drainage inlet & manhole […]


Construction Update: January 4, 2019

https://www.campbellclinic.com/construction-update-january-4-2019/

WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Continued work on west side private drive entrance. Continued underground storm drainage inlet and manhole lid placement. STATISTICS: The crane […]


Construction Update: December 28, 2018

https://www.campbellclinic.com/construction-update-december-28-2018/

WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placing underslab aggregate on east side. STATISTICS: The crane that will be used to hang all the structural steel arrived on site this week. It arrived […]