Category: Campbell Clinic expansion

Construction Update: March 18, 2019

https://www.campbellclinic.com/construction-update-march-18-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Continued decking the east half second and third floor decks. Poured stair no. 3. Began electrical overhead rough-in on third floor. Laid out sleeves on the east half second and third floor deck. Installed plumbing hangers and pipe on second […]


Construction Update: March 11, 2019

https://www.campbellclinic.com/construction-update-march-11-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Continued decking the east half second and third floor decks. Erected and detailed stair no. 3. Roughed in electrical overhead on third floor and laid out sleeves on the east half third floor deck. Installed plumbing hangers and pipe on […]


Construction Update: March 4, 2019

https://www.campbellclinic.com/construction-update-march-4-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Finished decking the west half roof. Began decking the east half second and third floor decks. Poured the fourth floor deck. Set and poured stair no. three. Laid out electrical wiring for lights on the first floor. Finished installing plumbing […]


Construction Update: February 25, 2019

https://www.campbellclinic.com/construction-update-february-25-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Finished decking the west half fourth floor. Began decking the west half roof. Poured the second floor deck. Prepped and poured the fourth floor deck. Finished installing electrical sleeves on the fourth floor deck. Continued installing plumbing sleeves on the fourth floor deck. Continued shipping […]


Construction Update: February 18, 2019

https://www.campbellclinic.com/construction-update-february-18-2019/

WORK PERFORMED THIS WEEK: Began erection of east half steel. Finished west half steel erection. Began decking the west half fourth floor. Poured the third floor deck. Prepped and poured the second floor deck. Finished installing electrical sleeves on the second floor deck. Finished installing plumbing sleeves on the second floor deck. Continued shipping and […]


Construction Update: January 28, 2019

https://www.campbellclinic.com/construction-update-1-28-19/

WORK PERFORMED THIS WEEK: Continued underground electrical. Continued shipping and staging steel. Continued west half steel erection. Brought electrical room block-out up to subgrade and prepped to pour. Continued installing the deck on the third floor of the west half steel. Continued work on west side private drive entrance. Continued work on the underground storm […]