May 20, 2019
WORK PERFORMED THIS WEEK: Shipped/staged/installed screen wall steel. Continued electrical overhead and in wall rough-in on the first and third floors. Continued underground feed for the generator power. Installed plumbing in wall and overhead rough-in on the first, second and third floors. Worked on rain leaders, wet columns and roof drains. Continued installation of high-pressure […]
Read moreApril 29, 2019
WORK PERFORMED THIS WEEK: Detailed stair no. 2. Installed HVAC curbs on the roof. Installed decking on the east half roof. Tied in-roof drains on the second floor. Shipped/staged/installed screen wall steel. Continued installing electrical overhead and in wall rough-in on the first and third floors. Continued installing wiring up the VAV boxes on the […]
Read moreApril 22, 2019
WORK PERFORMED THIS WEEK: Began detailing on stair no. 2. Installed HVAC curbs on the roof. Shipped, staged and installed curtain wall steel, and installed decking on the east half roof. Prepped and poured the second and third floor canopies. Continued electrical overhead and in wall rough-in on the first and third floors. Wired […]
Read moreApril 15, 2019
WORK PERFORMED THIS WEEK: Continued erection of east half steel canopies. Installed stair no. 2 and continued shipping and staging steel. Installed decking on the east half roof. Decked south side canopies. Prepped and poured the electrical/mechanical pads. Extended electrical overhead and in wall rough-in on the first and third floors. Continued underground electrical work […]
Read moreApril 8, 2019
WORK PERFORMED THIS WEEK: Continued erecting east half steel. Installed stair no. 2, and continued shipping and staging steel. Installed decking on the east half fourth floor and roof. Decked south side canopies. Prepped and poured the fourth floor east half slab. Installed electrical overhead and in wall rough-in on the first and third floors. […]
Read moreApril 1, 2019
WORK PERFORMED THIS WEEK: Continued erecting, shipping and staging east half steel. Installed decking on the east half fourth floor and roof. Prepped and poured stair no. 1. Prepped and poured cáfe area. Installed electrical overhead and in wall rough-in on the first and third floors. Laid out sleeves on the east half fourth floor […]
Read moreMarch 29, 2019
Ashley After years of suffering from lower back and radiating leg pain, Ashley decided to seek help. Before choosing an orthopaedic surgeon, she did her research. Both online reviews and her personal physician recommended Dr. Raymond Gardocki at Campbell Clinic. Before her endoscopic spine surgery, Ashley’s pain level was at a 7, and she couldn’t […]
Read moreMarch 25, 2019
WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Installed decking on the east half fourth floor and roof. Prepped and poured the east half second and third floor decks. Detailed stair no. 1 to be poured. Laid electrical overhead rough-in on the third floor. Laid out sleeves on […]
Read moreMarch 18, 2019
WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Continued decking the east half second and third floor decks. Poured stair no. 3. Began electrical overhead rough-in on third floor. Laid out sleeves on the east half second and third floor deck. Installed plumbing hangers and pipe on second […]
Read moreMarch 15, 2019
When you come to Campbell Clinic for physical therapy, you are likely to interact with one of our amazing physical therapy assistants (PTAs). It is hard to imagine our clinic without these diligent workers, but a little more than 50 years ago, the occupation didn’t even exist! While the idea for physical therapy assistants sparked […]