Category: facility expansion

Construction Update: June 3, 2019

https://www.campbellclinic.com/construction-update-june-3-2019/

WORK PERFORMED THIS WEEK: Installed elevator shaft steel. Continued electrical overhead and in-wall rough-in on the first through fourth floors. Continued underground feed for the generator power. Installed plumbing in wall and overhead rough-in on the first through fourth floors. Tied in roof drains. Installed mechanical drops in the fourth-floor operating rooms. Prepped for the […]


Construction Update: May 13, 2019

https://www.campbellclinic.com/construction-update-may-13-2019/

WORK PERFORMED THIS WEEK: Detailed stair no. 2. Shipped, staged and installed screen wall steel. Continued electrical overhead and in-wall rough-in on the first and third floors. Continued underground feed for the generator power. Installed wall and overhead rough-in on the first, second and third floors. Worked on rain leaders and wet columns. Continued layout […]


Construction Update: May 6, 2019

https://www.campbellclinic.com/construction-update-may-6-2019/

WORK PERFORMED THIS WEEK: Continued detailing stair no. 2. Continued shipping, staging and installing screen wall steel. Continued installing electrical overhead and in wall rough-in on the first and third floors. Continued installing wiring up the VAV boxes. Continue underground feed for the generator power. Plumbers installed in wall and overhead rough-in on the first, […]


Construction Update: March 4, 2019

https://www.campbellclinic.com/construction-update-march-4-2019/

WORK PERFORMED THIS WEEK: Continued erection of east half steel. Continued shipping and staging steel. Finished decking the west half roof. Began decking the east half second and third floor decks. Poured the fourth floor deck. Set and poured stair no. three. Laid out electrical wiring for lights on the first floor. Finished installing plumbing […]


Construction Update: February 11, 2019

https://www.campbellclinic.com/construction-update-february-11-2019/

WORK PERFORMED THIS WEEK: Installed deck on the second floor of the west half steel. Continued installing electrical sleeves on the second and third floor deck. Continued installing plumbing sleeves on the second and third floor deck. Continued shipping and staging steel. Continued west half steel erection. Continued pouring anchor bolt diamond blockouts. Prepped and […]


Construction Update: February 4, 2019

https://www.campbellclinic.com/construction-update-february-4-2019/

WORK PERFORMED THIS WEEK: Continued underground electrical in the parking lots. Began plumbing work on the first floor restrooms. Continued shipping and staging steel. Continued west half steel erection. Installed stair tower on southwest corner of the building. Began installing sleeves on elevated decks of the west half steel. Poured electrical room blockout. Began pouring […]


Construction Update: January 18, 2019

https://www.campbellclinic.com/construction-update-january-18-2019/

WORK PERFORMED THIS WEEK: Continued underground electrical. Continued shipping and staging steel. Continued west half steel erection. Set west half stairs. Began installing the deck on floors two and three of the west half steel. Began excavation and installation of canopy foundations. Poured canopy foundations. Continued work on west side private drive entrance. Continued underground […]


Construction Update: January 10, 2019

https://www.campbellclinic.com/construction-update-january-10-2019/

WORK PERFORMED THIS WEEK: Continued underground electrical & plumbing. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Poured the east half slab. Continued work on west side private drive entrance. Continued underground storm drainage inlet & manhole […]


Construction Update: January 4, 2019

https://www.campbellclinic.com/construction-update-january-4-2019/

WORK PERFORMED THIS WEEK: Continued underground plumbing and electrical. Continued shipping and staging steel. Continued west half steel erection. Prepped east half of the building pad for slab pour. Placed underslab aggregate on east side. Continued work on west side private drive entrance. Continued underground storm drainage inlet and manhole lid placement. STATISTICS: The crane […]